Jeep Grandee Cheroki + Jeep Grand Cherokee brand Cars + Settings and routine maintenance + Ryadny six-cylinder engine + V8 Engine + Procedures of the general and major maintenance of the engine + Systems of cooling, heating and air conditioning + the Power supply system and production of the fulfilled gases + System of electric equipment of the engine + Systems of decrease in toxicity of the fulfilled gases and engine management + Manual box of gear shifting + Automatic transmission + Transfer case - Coupling and transmission line General information Coupling - the general description and check of serviceability of functioning Removal and installation of components of hydraulic system of switching off of coupling Removal, check of a condition and installation of components of coupling Removal, check of a condition and installation of the vyzhimny bearing of coupling Check of a condition and replacement of the directing bearing Driveshafts, differentials and bridges - the general information Check of a condition of the transmission line Removal and installation of driveshafts Replacement of kardanny hinges Replacement of an epiploon of a shaft of a leading gear wheel of differential Removal, service and installation of a nave and bearings (forward wheel) Removal, major maintenance and installation of a forward power shaft Removal and installation of assembly of the forward bridge Removal and installation of a back semi-axis and bearing assembly Removal and installation of assembly of the back bridge + Brake system + Suspension bracket and steering + Body + System of onboard electric equipment + Governing bodies and operation receptions
|
Removal and installation of a back semi-axis and bearing assembly
Removal
|
- Weaken nuts of fastening of a wheel, поддомкратьте a back of the car and establish it on props. Remove a wheel.
- Remove a brake drum, then give nuts of fastening of a board of the brake mechanism.
|
- To Otbolita four nuts of fastening of a board of the brake mechanism using a head with the extension piece through an opening in a wheel nave.
|
- Connect a hammer with sliding brisk and a nozzle to a flange of a semi-axis and take the last from a bridge sleeve.
|
- Take a semi-axis from a bridge sleeve by means of a hammer with sliding brisk and nozzles on an axis flange.
|
- If the bearing is subject to replacement, deliver assembly in a workshop of car-care center or dealer office for removal of the old bearing and a press fitting on its new. At installation of the new bearing take care also of replacement of an external epiploon of a semi-axis (see the following item).
- If on a board of the brake mechanism there are traces of leakages of greasing of differential, it is necessary to replace an external epiploon of a semi-axis. Remove an old epiploon by means of a hammer with sliding brisk and a stripper in internal captures. A new epiploon plant by means of the special tool or a piece of a pipe of suitable diameter.
|
- Take a semi-axis epiploon from a bridge sleeve by means of a hammer with sliding brisk with the stripper attached to it with internal captures.
|
|
- Grease epiploon sponges, then fill an epiploon on the place by means of the special tool or the pipe piece which external diameter will be slightly less external diameter of an epiploon.
|
|
|
Installation
|
- Wipe a bearing nest in a bridge sleeve. Fill the bearing special (for wheel bearings) greasing, put also thin layer of greasing on an external surface of the bearing.
- Grease sponges of an internal epiploon, then fill a semi-axis in a bridge sleeve, trying to hold it coaxially with the last not to damage an epiploon.
- Establish nuts of a board of the brake mechanism, strongly tighten them. Put on a brake drum a bridge flange.
- Establish a wheel and strongly tighten nuts of its fastening. Lower the car on the earth and tighten nuts of fastening of a wheel with demanded effort (see. Specifications to Head of Control and routine maintenance).
|
|
|
|